Complexity of the ELSP with general cyclic schedules

Research output: Contribution to journal › Journal Article › peer-review

Abstract

We show that the Economic Lot Schedule Problem (ELSP) is NP-hard in the strong sense under General Cyclic Schedules (GSC), Zero-Inventory Cyclic Schedules (ZICS), Time-Invariant Cyclic Schedules (TICS), Lot-Invariant Cyclic ScheduJes (LICS), and Basic Period Cyclic Schedules (BPCS).

Original languageEnglish
Pages (from-to)109-113
Number of pages5
JournalIIE Transactions (Institute of Industrial Engineers)
Volume29
Issue number2
DOIs
Publication statusPublished - 1997
Externally publishedYes

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 9 - Industry, Innovation, and Infrastructure
    SDG 9 Industry, Innovation, and Infrastructure

Fingerprint

Dive into the research topics of 'Complexity of the ELSP with general cyclic schedules'. Together they form a unique fingerprint.

Cite this